Driving Logic on the S2 // Diagnostics Tab
Use Driving Logic to analysis only those path(s) that are driving the schedule through to completion. This allows you to pinpoint the key activities in a schedule.
By default, the logic trace runs in Driving Logic Only mode.
Example of Driving Logic
The screenshot below shows an example of a driving logic analysis looking at all driving activities leading into and stemming from an activity called EPC Design. The activities in this path analysis are also shown in the ribbon browser and the results in the ribbon/phase analyzer are reflective of this driving path.